未參加 EHSS、車位又沒有預留掣位的舊式屋苑。技術上不算最難,因為停車場本身已有電源;真正令你停滯的是管理處及業主立案法團。大部分人不是被拒絕,而是卡在「補件循環」——交一次少一樣,每補一次就等多一次會議。An older estate that never joined EHSS and has no outlet at the bay. Technically it isn't the hardest — the carpark has power. What stalls you is management and the owners' committee. Most people aren't refused; they're stuck in the missing-document loop, where each round of one more requirement costs another meeting cycle.

法團一年可能只開幾次會。每一次補件,實際代價不是幾日,而是下一次會議。A committee may only meet a handful of times a year. The real cost of a missing document isn't a few days — it's the next meeting.
量度電掣房至車位的走線距離、確認停車場現有容量及走線路線。這一類個案走線由 5 米到 60 米都有,所以一定要看過現場才開價。We measure the run from the switch room to your bay, confirm the carpark's spare capacity and plan the route. Runs in this category range from 5m to 60m, which is exactly why we quote after seeing it.
安裝圖則及走線圖、電力負載計算(現有尖峰、加裝後用量、餘量)、EMSD 註冊電業承辦商及工程人員牌照副本、2 千萬公眾責任保險證明、充電樁 CE / EMC / LVD 測試報告、保護裝置說明。最後兩項通常冇人主動交,但正正是回應「會唔會有火警風險」的關鍵。Drawings and cable routing, load calculations (existing peak, demand after, headroom left), EMSD contractor and worker licence copies, the HK$20M public liability certificate, the charger's CE / EMC / LVD reports, and a protective-devices note. Nobody volunteers those last two — and they're exactly what answers the fire-risk question.
這一步的時間完全不在我們手上。如有需要,我們可以出席法團會議直接解答技術問題 —— 通常比書面來回快得多。This step is entirely out of our hands. If it helps, we can attend the meeting and answer the technical questions in person, which is usually far quicker than another round of correspondence.
持牌電工施工,走線收納於天花線槽,半日完成。之後同電力公司夾期掛獨立電錶,並交付 WR1 完工證明書及電力測試紀錄。Licensed electricians, cabling concealed in ceiling trunking, half a day on site. We then book the utility for the dedicated meter and hand over the WR1 certificate and test records.
一句總結In one line
舊式屋苑的工夫在文件,不在工程。第一次就把法團會問的東西全部交齊,通常兩星期內獲批;逐樣補,隨時拖幾個月。In an older estate the work is paperwork, not engineering. Submit everything the committee will ask for the first time and approval usually lands within two weeks. Feed it to them one document at a time and it can drag for months.
其他類型The other types

電力基礎已備妥,接駁最直接Infrastructure is in place — the most direct connection
睇詳細流程 →See the steps →
唔使人批,但要等中電,約 2–3 個月No approvals needed, but CLP takes 2–3 months
睇詳細流程 →See the steps →
有預留掣位,改裝成專用充電線路An outlet is already there — converted to a dedicated circuit
睇詳細流程 →See the steps →