首頁Home / 安裝案例Cases / 元朗・獨立屋Yuen Long · Detached

三相電升級 22kWThree-phase upgrade, 22kW

原有電錶容量不足,即使加裝 7kW 亦會跳掣。我們代辦三相電升級申請,獲批後安裝 22kW,充電時間大幅縮短。The old meter couldn't even take 7kW without tripping. We filed the three-phase upgrade; once approved, 22kW cut the charge time sharply.

三相電升級 22kW

現場情況

元朗一間獨立屋,兩夫婦各有一部電動車,共用一個車位(一前一後泊)。原有電錶是單相 60A,全屋兩部冷氣、電熱水爐、焗爐、洗衣乾衣機。

業主原本只想裝一支 7kW,但我們做完負載評估之後,建議他先停一停。

最棘手的地方

負載評估的結果是:連 7kW 都唔夠。

計算如下:

  • 電錶總容量:60A
  • 全屋尖峰同時用電(實測):約 38A(夏天晚上,兩部冷氣 + 熱水爐 + 煮食)
  • 餘下可用:約 22A
  • 7kW 充電樁需要:32A

即是說,夏天晚上一邊開冷氣一邊充電,一定跳掣。而業主有兩部車,實際需求還要更高。

這種情況如果照裝,客戶會在入伙第一個夏天不斷跳掣,然後回頭怪安裝公司。所以我們選擇先講清楚。

三個選項,我們攤開比較

選項 A:裝 7kW,但限流到 16A(3.5kW) 最平,即日可做。但兩部車輪流充,每晚只能補約 35 度,夏天還是要小心用電。業主覺得太將就。

選項 B:加大單相電錶到 100A 中價位。可以支援一支 7kW,但兩部車同時充電仍然不行,而且將來冇再升級的空間。

選項 C:升級三相電 最貴,時間最長。但做到之後可以上 22kW,兩部車輪流充各自都好快,而且全屋負載一次過解決。

業主選了 C —— 因為他計過,兩部車的長期使用值回差價。

我們點做

1. 代辦三相電申請 準備負載計算、單線圖及申請文件,交予電力公司。這一步是整個工程最花時間的部分,需要等候電力公司排期及審批。

2. 更換電錶箱及主線 三相電需要更換供電線、電錶箱及主開關。這部分與電力公司協調停電時間,一日內完成。

3. 配電箱重整 新增三相專用回路給充電樁,配 Type A 30mA 漏電開關;同時整理原有回路,把熱水爐同冷氣分佈到不同相位,令三相負載平均。

4. 安裝 22kW 充電樁 Wall Case 3 三相版本,內置 6mA 直流漏電偵測。

結果

由申請到完工,總共約十星期,當中大部分是等候電力公司審批的時間 —— 實際施工只有兩日。

完成後:22kW 之下,一部 60 度電的車由 20% 充到 80% 約需 1.6 小時。兩部車一晚順序充完仍然綽綽有餘,而且夏天開足冷氣同時充電亦不會跳掣。

這個案例適合誰參考

如果你有以下任何一項,值得考慮三相:

  • 一個車位兩部電動車
  • 電錶已經是 60A 或以下,而全屋電器不少
  • 本身已經因為其他原因要處理電力問題

但要有心理準備:三相升級的時間成本比金錢成本更難預計,因為要等電力公司。想做的話,早點開始申請。

想知道你屋企的負載夠唔夠?WhatsApp 傳一張電錶相同你的電器清單給我們,我們幫你計。

The site

A detached house in Yuen Long. A couple with one EV each, sharing a single bay (parked nose to tail). The existing supply was single-phase 60A, serving two air conditioners, an electric water heater, an oven, and a washer-dryer.

The owner originally just wanted one 7kW charger. After the load assessment, we suggested pausing.

The hard part

The assessment said even 7kW wouldn't fit.

The maths:

  • Meter capacity: 60A
  • Measured household peak demand: about 38A (summer evening — two aircons, water heater, cooking)
  • Headroom: about 22A
  • A 7kW charger needs: 32A

So charging on a summer evening with the aircon on would trip, guaranteed. And with two cars, real demand was higher still.

Installing anyway would have meant the customer tripping breakers all through their first summer and then blaming the installer. We'd rather say it up front.

Three options, laid side by side

Option A: fit 7kW but limit it to 16A (3.5kW). Cheapest, same-day. But with the cars taking turns, each night adds only about 35 kWh and they'd still have to watch their usage in summer. The owner felt it was too much of a compromise.

Option B: enlarge the single-phase meter to 100A. Mid-price. Supports one 7kW charger, but still can't run both cars together, and leaves no headroom to upgrade later.

Option C: go three-phase. Most expensive, longest lead time. But it unlocks 22kW, charges both cars quickly in turn, and solves the whole house's capacity in one move.

The owner chose C, having worked out that two cars over the long run justified the difference.

What we did

Filed the three-phase application. Load calculations, single-line diagram and application documents to the utility. This is the slowest part of the whole job — it waits on the utility's scheduling and approval.

Replaced the meter box and main supply. Three-phase needs a new supply cable, meter box and main switch. Coordinated the outage window with the utility and completed it in a day.

Reorganised the distribution board. Added a dedicated three-phase circuit for the charger with a Type A 30mA RCD, and redistributed the existing circuits so the water heater and aircons sit on different phases and the load balances across all three.

Installed the 22kW unit. Three-phase Wall Case 3, with 6mA DC leakage detection built in.

The outcome

About ten weeks from application to completion, most of it waiting on utility approval — actual site work was two days.

Afterwards: at 22kW a 60kWh car goes from 20% to 80% in roughly 1.6 hours. Both cars charge in sequence overnight with room to spare, and running the aircon flat out while charging no longer trips anything.

Who this case is useful for

Three-phase is worth considering if any of these apply:

  • Two EVs on one bay
  • A 60A or smaller meter with a decent number of appliances in the house
  • You already need electrical work done for other reasons

But go in expecting this: with a three-phase upgrade, the time cost is harder to predict than the money cost, because it waits on the utility. If you want it, start the application early.

Want to know whether your supply is enough? WhatsApp us a photo of the meter and a list of your appliances, and we'll work it out.

你的物業與這個案例相似?Does your place look like this one?

傳送車位及電錶相片,我們會告知最接近哪一種情況、需時多久及費用多少。Send photos of your bay and meter. We'll tell you which case yours resembles, how long, and how much.

其他案例More cases

您好!請留下您的車位地址及車位相,即時報價。Hi! Send us your bay address and a photo for an instant quote.